Hudson Yards Stakeholders Dive into NYC’s ‘Newest Neighborhood’ at CO Event

What kind of work goes into rebuilding and renewing a massive chunk of Manhattan, spanning from the High Line up to Hell’s Kitchen and Eighth Avenue over to the Hudson River?

That was the question posed to a select group of developers, architects, engineers and officials helming the transformation of Manhattan’s Far West Side, who gathered at Commercial Observer’s “The Hudson Yards District: New York’s Newest Neighborhood” conference earlier this month to discuss the various commercial and infrastructure developments that are recreating an entire swath of the island.

The event, held on March 8 at law firm Herrick Feinstein’s offices at 2 Park Avenue near Murray Hill, was kicked off with remarks from Patrick O’Sullivan, a partner in the firm’s real estate department. O’Sullivan, a former executive at the New York City Economic Development Corporation, recalled how the development of Hudson Yards was preceded by the proposed West Side Stadium, which was part of the city’s unsuccessful bid to host the 2012 Summer Olympics. After the Olympic bid (which was awarded to London) failed, O’Sullivan said, New York “went to plan B—and it was definitely a good one.”

That “plan B”—most significantly the Hudson Yards mixed-use mega-development helmed by Related Companies and Oxford Properties Group—was the subject of the morning’s first panel, which featured Andrew Cantor, a senior vice president at Related; Andrew Werner, a senior associate principal at architecture firm and Hudson Yards master planner Kohn Pedersen Fox Associates; Colin Brown, a principal at engineering firm Thornton Tomasetti; and Mitchell Moinian, a principal at The Moinian Group, which is developing its own Hudson Yards office tower at 3 Hudson Boulevard.

With Phase 1 of Related and Oxford’s 28-acre Hudson Yards project roughly one year away from opening, Cantor recalled the process that has facilitated the evolution of a neighborhood that historically was “always seen as too far away” from the rest of Manhattan into one that has “changed the way many people view” the possibilities for development in New York City.

Werner noted the “mixed-use” aspect of the project, which seeks to bring residential, commercial and retail uses all within close proximity of each other with the goal of building a “24-hour neighborhood.” From an architectural perspective, Werner said the multi-tower development sought a design with “texture” that would “drive people to want to be there”—a daunting task, considering the site was a “tabula rasa,” or blank slate, that forced KPF to draw on its experiences building “large-scale cities from scratch” in Asia.

Brown, whose firm handled engineering for much of the Related and Oxford project, cited the “great challenge” of building on a site that was an operational railyard—constraints that made it “hard not to be innovative [in order] to make something work,” and called for out-of-the-box solutions like suspending the development’s retail podium above the railyards and building from there.

Moinian was quick to point out that while the Related and Oxford project occupies several square blocks south of West 34th Street, half of the Hudson Yards district at large is located above the thoroughfare, stretching up to West 41st Street. The district at large, he said, will provide newfound “connectivity from Midtown [down] to the Meatpacking District.”

While acknowledging that The Moinian Group’s 2-million-square-foot 3 Hudson Boulevard, which sits on the north side of West 34th Street, won’t be able to take advantage of the “mini-city infrastructure in place for [Related and Oxford’s] mini-city,” the tower will benefit from the development of Hudson Boulevard Park, which will run from West 34th to West 37th Streets, Moinian said. The developer has commenced work on the foundation of the FXCollaborative-designed office building “on spec,” with no advance agreements with office tenants in place—something that shows the extent to which The Moinian Group “obviously believe[s] in the neighborhood,” he added.

hudson yards panels 90 Hudson Yards Stakeholders Dive into NYC’s Newest Neighborhood at CO Event
From left: Robin Stout, Michael Evans and Henry Caso at CO’s “The Hudson Yards District: New York’s Newest Neighborhood” conference on March 8. Photo: Aaron Adler/for Commercial Observer

The second and final panel of the morning focused on the area’s infrastructure, and the developments and improvements taking place to bolster the Hudson Yards district’s transportation offerings and connectivity. Those include the ambitious redevelopment of the James A. Farley Post Office Building into the new Moynihan Train Hall—a project decades in the making that seeks to build “the Grand Central Terminal of the West Side” while relieving the notorious congestion that affects the neighboring Pennsylvania Station, according to Michael Evans, the president of the Moynihan Station Development Corporation.

Work on Moynihan Train Hall is scheduled for completion in early 2021, and Evans cited the logistical obstacles involved when “working within the busiest train station in the Western Hemisphere.” But the project is expected to increase concourse capacity at Penn Station “by 50 percent overnight,” Evans said, and build momentum for further, “critical” infrastructure improvements at the transit hub deridingly referred to by New York Governor Andrew Cuomo as “the catacombs.”

Further west, the Jacob K. Javits Convention Center is in the midst of its own major overhaul, as detailed by Robin Stout, the president of the New York Convention Center Development Corporation. The four-year, $1.2 billion project seeks to expand the convention center’s roughly 400,000 square feet of exhibition space to 500,000 square feet in order “to attract the largest shows,” Stout said.

The expansion will also add 50,000 square feet of new meeting room and breakout room space, as well as a new 6,000-person capacity ballroom that will be “the largest ballroom in the northeast,” according to Stout. There will also be upgrades to the Javits Center’s infrastructure, including a new three-story electrical transformer building and a new truck-marshalling facility that will be built on West 40th Street.

“We don’t want people to think of Javits as low-rise protection for Hudson Yards’ river views,” Stout said. He added the convention center, and the commerce it will bring to the Far West Side, will spur further hotel and retail development and help Hudson Yards achieve its goal of becoming “a vibrant 24-hour neighborhood.”

Source: commercial

Cheezus: Artisanal Is Not Returning to Park Avenue (South)

Artisanal Fromagerie Bistro, which filed for bankruptcy in March 2017 shortly before it was slated to open at its new home on Park Avenue South, is no longer bowing.

Its 10,550-square-foot TF Cornerstone space (7,550 square feet at grade and 3,000 square feet—usable—in the basement) at the base of the 12-story office building at 387 Park Avenue South is now back on the market with an asking rent of $225 per square foot, a spokeswoman for the landlord told Commercial Observer. She declined to respond to questions about Artisanal but signage for the bistro was dismantled recently.

Winick Realty Group’s Aaron Fishbein, who is the broker for the retail space at the 215,000-square-foot building along with colleague Steven Baker, said they got possession of the Artisanal space in the beginning of January. He, too, declined to talk about Artisanal except to say that Barry’s Bootcamp took 4,600 square feet of the 12,150-square-foot ground-floor space and Artisanal took the balance of it, as well as the basement.

In February 2015, the landlord of 2 Park Avenue, Morgan Stanley, decided not to renew Artisanal’s lease, the same month Artisanal formed a new ownership entity with Artisanal owner Stephanie Schulman, who is romantically linked to the previous owner Vincent S. Bonfittodrory, a.k.a. Sarid Drory. As CO reported in November 2015, Artisanal signed a lease to relocate to 285 PAS from 2 Park Avenue.

The cheese-focused brasserie was initially going to open in the new digs on Park Avenue South between East 27th and East 28th Streets in summer 2016. The company filed for Chapter 11 bankruptcy in August 2016 and then again in March 2017. The latter one—in which Artisanal allegedly owes its former landlord over $3 million for unpaid rent, etc.—is still ongoing. The summer 2016 opening date got delayed to June 2017, and those plans have faded away. Meanwhile, Artisanal’s website doesn’t reflect a change in plans.

“Their plan to leave all their liabilities with the old entity did not work,” weighed in Adam Stein-Sapir, a co-managing partner of Pioneer Funding Group, which specializes in analyzing and investing in bankruptcy cases, and who is not involved in the case. “Also because of the controversy over the first filing they may have had trouble raising new money to open the second restaurant.”

The developer acquired the pre-war building in 2005 and gave it a makeover in early 2015, including a glass facade from the base to the third floor, and renovations to the lobby, elevators and roof deck featuring a glass penthouse.

A. Mitchell Greene of Robinson Brog Leinwand Greene Genovese & Gluck, the attorney for the eatery during the March 2017 bankruptcy, didn’t respond to requests for comment.